Defense Waste Processing Facility (DWPF) Documents

 

Document Number

Document Title

Dated

1

A01 N-AA-S-00001 Rev 7

DWPF Authorization Agreement

Aug. 2015

2

A02 QARD DOE-RW-0333P Rev 21

DOE OCRWM Quality Assurance Requirements and Description

Jan. 2019

3

A03 S-EHA-S-00001 Rev 13

Emergency Planning Hazards Assessment for the DWPF

Jul. 2016

4

A04 U-ESS-S-00001 Rev 2

Evaluation of the Safety of the Situation (ESS): Melter Feed Rate Temperature Correlation Basis (PISA PI-2014-0009)

Dec. 2016

5

A05 U-ESS-S-00002 Rev 2

Evaluation of the Safety of the Situation (ESS): Retained Hydrogen in DWPF Vessels (PISA PI- 214-0013)

Dec. 2016

6

A06 U-JCO-S-00002

Rev 1 Defense Waste Processing Facility Justification for Continued Operation

Aug. 2015

7

A07 WSRC-IM-91-116-6 Rev 9

DWPF Glass Product Control Program

Sep. 2018

8

A08 WSRC-SA-6-Vol-1 Rev 37 (Ch 1,2)

DWPF Final Safety Analysis Report

Nov. 2018

9

A09 WSRC-SA-6-Vol-2 Rev 37 (Ch 3)

DWPF Final Safety Analysis Report

Nov. 2018

10

A10 WSRC-SA-6-Vol-3 Rev 37 (Ch 4)

DWPF Final Safety Analysis Report

Nov. 2018

11

A11 WSRC-SA-6-Vol-4 Rev 37 (Ch 5)

DWPF Final Safety Analysis Report

Nov. 2018

12

A12 WSRC-SA-6-Vol-5 Rev 37 (Ch 6-8)

DWPF Final Safety Analysis Report

Nov. 2018

13

A13 WSRC-SA-6-Vol-6 Rev 37 (Ch 9)

DWPF Final Safety Analysis Report

Nov. 2018

14

A14 WSRC-SA-6-Vol-7 Rev 37 (Ch 10)

DWPF Final Safety Analysis Report

Nov. 2018

15

A15 WSRC-SA-6-Vol-8 Rev 37 (Ch 11)

DWPF Final Safety Analysis Report

Nov. 2018

16

A16 WSRC-SA-6-Vol-9 Rev 37 (Ch 12-14)

DWPF Final Safety Analysis Report

Nov. 2018

17

A17 X-SD-G-00005 Rev 35

Waste Compliance Plan for Radioactive Liquid Waste Transfer from DWPF to H Tank Farm

Sep. 2018

18

A18 X-SD-G-00008 Rev 27

Waste Compliance Criteria for Sludge, ARP, and MCU Process Transfers to 512-S and DWPF

Oct. 2018

19

A19 SRNL-STI-2013-00343 Rev 0

FY13 Glycolic-Nitric Acid Flowsheet Demonstrations of the DWPF Chemical Process Cell with Stimulants

Mar. 2014

20

A20 Y-AES-S-00002 Rev 0

Defense Waste Processing Facility Mercury Removal Study

Sep. 2015

21

A21 X-ESR-S-00258 Rev 0

Literature and Data Review for Evaluating the Production of Dimethyl Mercury in the Defense Waste Processing Facility

May 2015

22

A22 SRNL-STI-2009-00120 Rev 0

Selection and Preliminary Evaluation of Alternative Reductants for SRAT Processing

Jun. 2009

23

A23 SRNL-STI-2010-00523 Rev 0

Glycolic-Formic Acid Flowsheet Development

Sep. 2010

24

A24 SRNL-STI-2010-00523 Rev 1

Glycolic-Formic Acid Flowsheet Final Report for Downselection Decision

Mar. 2011

25

A25 SRNL-STI-2012-00018 Rev 1

Glycolic-Nitric Acid Flowsheet Demonstration of the DWPF Chemical Process Cell with Sludge and Supernate Simulants

Aug. 2012

26

A26 X-ESR-S-00279 Rev 1

Phase 2 Report - Mercury Behavior in the Defense Waste Processing Facility

Jul. 2016

27

A27 U-SBS-S-0003 Rev 3

Safety Basis Strategy Defense Waste Processing Facility Alternate Reductant Project

Jul. 2017

28

A28 WSRC-IM-91-116-0 Rev 12

DWPF Waste Compliance Plan

Sep. 2018

29

A29 M-501 Rev 5

Technical Specifications for Melter Vessel for the Defense Waste Processing Facility

Feb. 2005

30

A30 P-501 Rev 6

Technical Specification for Melter External Piping for the Defense Waste Processing Facility

Feb. 2007

31

A31 S-501 Rev 2

Technical Specification for Structural Stainless Steel for Melter Assembly Support Frames for the Defense Waste Processing Facility

Feb. 2005

32

A32 E-501 Rev 6

Technical Specification for Melter Assembly Cable and Connectors

Feb. 2007

33

A33 M-500 Rev 6

Technical Specifications for Melter Vessel Assembly for the Defense Waste Processing Facility

Jan. 2008

34

A34 M-502 Rev 7

Technical Specification for Melter Vessel Assembly (Split Scope) for the Defense Waste Processing Facility

Jan. 2008

35

A35 N-NCS-S-00007 Rev 17

Nuclear Criticality Safety Analysis Summary Report: Salt Solution and Sludge Operations in 512-S Facility and DWPF

Apr. 2018

36

A36 WSRC-TS-95-0019 Rev 66

DWPF Technical Safety Requirements

Oct. 2019


Effluent Treatment Facility (ETF) Documents

 

Document Number

Document Title

Dated

1

Reserved

 

2

B02 S-CLC-H-00710 Rev 0

ETF Radiological and Chemical Hazards identification

May 1999

3

B03 S-EHA-H-00010 Rev 1

Emergency Planning Hazards Assessment

Nov 2011

4

B04 WSRC-IM-94-10 Rev 774

LWD/WS Projects Safety Basis Manual

Jan. 2020

5

B05 WSRC-TR-98-00379 Rev 16

Auditable Safety Analysis

Jun 2014

6

B06 WSRC-TR-99-00009 Rev 3

F-H Tank Farms Waste Compliance Plan for Transfers to ETF

Aug. 2001

7

B07 X-WCP-H-00002 Rev 17

F/H Effluent Treatment Project Waste Concentrate Regular Waste Compliance Plan

Sep. 2019

8

B08 X-EPF-H-00016 Rev 0

Path Forward for the Reduction of Mercury Vapors in ETP Operation Areas

Jun. 2016


Functional Service Agreements

 

Document Number

Document Title

Dated

1

C01 G-FSP-G-00002 Rev 7

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Safeguards, Security and Emergency Services (SS&ES)

Mar. 2016

2

C02 G-FSP-G-00004 Rev 4

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Utilities

Oct. 2012

3

C03 G-FSP-G-00005 Rev 9

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Infrastructure Services

Oct. 2013

4

C04 G-FSP-G-00006 Rev 6

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC -Environment, Safety, Security and Health Base Load Services

Oct. 2014

5

C05 G-FSP-G-00007 Rev 5

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Supply Chain Management Services

Oct. 2014

6

C06 G-FSP-G-00008 Rev 5

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Analytical Services

Sep. 2014

7

C07 G-FSP-G-00009 Rev 8

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Information Technology

Mar. 2016

8

C08 G-FSP-G-00010 Rev 5

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Project Management & Construction Services

Oct. 2012

9

C09 G-FSP-G-00011 Rev 7

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Engineering Services

Oct. 2014

10

C10 G-FSP-G-00012 Rev 4

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - SRNL Services

Oct. 2014

11

C11 G-FSP-G-00013 Rev 8

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Quality Assurance, Contractor Assurance and Site-Wide Procedures Services

Oct. 2015

12

C12 G-FSP-G-00015 Rev 5

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Public Affairs Services

Oct. 2014

13

C13 G-FSP-G-00016 Rev 6

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Enterprise Controls and Support Services

Mar. 2016

14

C14 G-FSP-G-00017 Rev 4

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Solid Waste Management

Oct. 2013

15

C15 G-FSP-G-00018 Rev 4

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Waste Disposal Support

Oct. 2014

16

C16 G-FSP-G-00019 Rev 8

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC -Liquid Waste Receipt Services

Oct. 2015

17

C17 G-FSP-G-00071 Rev 2

Functional Service Agreement Between Savannah River Nuclear Solutions LLC and Savannah River Remediation LLC - Site Training Services

Oct. 2012


Section 3116 Determinations

 

Document Number

Document Title

Dated

1

D01 DOE-SRS-WD-2012-001 Rev 0

Basis for Section 3116 Determination for Closure of F-Tank Farm at the Savannah River Site

Mar. 2012

2

D02 DOE-SRS-WD-2014-001 Rev 0

Basis for Section 3116 Determination for Closure of H-Tank Farm at the SRS

Dec. 2014

3

D03 DOE-WD-2005-001

Basis for Section 3116 Determination for Salt Waste Disposal at the SRS

Jan. 2006


National Environmental Policy Act (NEPA) Documents

 

Document Number

Document Title

Dated

1

E01 DOE-EIS-0082-S2-SA-01

Supplement Analysis Salt Processing Alternatives at the SRS

Jan. 2006

2

E02 DOE-EIS-0303-SA-01

High-Level Waste Tank Closure Final Environmental Impact Statement for the SRS - Supplement Analysis

Mar. 2012

3

E03 DOE-EIS-0303-SA-02

High-Level Waste Tank Closure Final Environmental Impact Statement for the SRS - Supplement Analysis

Aug. 2014

4

E04 DOE-EIS-0082-S2

SRS Salt Processing Alternatives Final Supplemental Environmental Impact Statement

Jun. 2001

5

E05 DOE-EIS-0082 UC-70

Final Environmental Impact Statement for Defense Waste Processing Facility

Feb. 1982

6

E06 DOE-EIS-0303

High-Level Waste Tank Closure Final Environmental Impact Statement

May 2002

7

E07 DOE-EIS-0303-ROD

Record of Decision for DOE SRS High-Level Waste Tank Closure (Federal Register Vol 67, No. 160, Aug 19, 2002) Notices

Aug. 2002

8

E08 FONSI HLW Tank Closure

Finding of No Significant Impact for the Closure of the H-Level Waste Tanks in F- and H-Areas at the SRS

Jul. 1996

9

E09 DOE-EIS-0200-F

Final Waste Management Programmatic Environmental Impact Statement for Managing Treatment, Storage, and Disposal of Radioactive and Hazardous Waste - Summary

May. 1997

10

E10 EIS-0217 Volume 1-1

SRS Waste Management Final Environmental Impact Statement Volume 1 (1st third of document)

Jul. 1995

11

E11 EIS-0217 Volume 1-2

SRS Waste Management Final Environmental Impact Statement Volume 1 (2nd third of document)

Jul. 1995

12

E12 EIS-0217 Volume L1-3

SRS Waste Management Final Environmental Impact Statement Volume 1 (last third of document)

Jul. 1995

13

E13 EIS-0217 Volume 2-1

SRS Waste Management Final Environmental Impact Statement Volume II (1st half of document)

Jul. 1995

14

E14 EIS-0217 Volume 2-2

SRS Waste Management Final Environmental Impact Statement Volume 1I (2nd half of document)

Jul. 1995

15

E15 EIS-0062

Final EIS Waste Management Operations

Apr. 1980

16

E16 EIS-0082-S

Final Supplemental EIS DWPF

Nov. 1994

17

E17 EIS-0082-S2

Final Supplemental EIS Salt Processing Alternatives - Summary

Jun. 2001

18

E18 EIS-0082-S2-1

Final Supplemental EIS Salt Processing Alternatives - Part 1

Jun. 2001

19

E19 EIS-0082-S2-2

Final Supplemental EIS Salt Processing Alternatives - Part 2

Jun. 2001


Standards/Requirements Identification Documents

 

Document Number

Document Title

Dated

1

F01 SRR-RP-2009-00558-001

Rev 19-08 Management Systems FA 01.0


Jan. 2020

2 F02 SRR-RP-2009-00558-002 Rev 18-09 Quality Assurance FA 02.0 Jun. 2018
3 F03 SRR-RP-2009-00558-003 Rev 19-05 Configuration Management FA 03.0 Nov. 2019
4 F04 SRR-RP-2009-00558-004 Rev 14-03 Training and Qualifications FA 04.0
Feb. 2015
5 F05 SRR-RP-2009-00558-005 Rev 19-09 Emergency Management FA 05.0
Dec. 2019
6 F06 SRR-RP-2009-00558-006 Rev 09-08 Safeguards and Security FA 06.0
Jul. 2009
7 F07 SRR-RP-2009-00558-007 Rev 19-06 Engineering Program FA 07.0
Nov. 2019
8 F08 SRR-RP-2009-00558-008 Rev 14-04 Construction Program FA 08.0
Mar. 2015
9 F09 SRR-RP-2009-00558-009 Rev 18-10 Conduct of Operations FA 09.0
Nov. 2018
10 F10 SRR-RP-2009-00558-010 Rev 18-05 Maintenance FA 10.0
Sep. 2018
11 F11 SRR-RP-2009-00558-011 Rev 14-11 Radiation Protection FA11.0
Feb. 2015
12 F12 SRR-RP-2009-00558-012 Rev 15-03 Fire Protection FA 12.0
Nov. 2015
13 F13 SRR-RP-2009-00558-013 Rev 17-02 Packaging and Transportation FA 13.0
May 2017
14 F14 SRR-RP-2009-00558-014 Rev 18-06 Environmental Restoration FA 14.0
Oct. 2018
15 F15 SRR-RP-2009-00558-015 Rev 18-07 Facility Disposition FA 15.0
Oct. 2018
16 F16 SRR-RP-2009-00558-016 Rev 14-15 Waste Management FA 16.0
Feb. 2015
17 F17 SRR-RP-2009-00558-017 Rev 09-19 Research and Development & Experimental Activities FA 17.0
Jul 2009
18 F18 SRR-RP-2009-00558-018 Rev 19-07 Nuclear Process Safety FA 18.0
Oct 2019
19 F19 SRR-RP-2009-00558-019 Rev 18-12 Occupational Safety and Health FA 19.0
Feb 2019
20 F20 SRR-RP-2009-00558-020 Rev 17-09 Environmental Protection FA 20.0
Nov 2017
21 F21 SRR-RP-2009-00558-000 Rev 19-01 SRID Purpose and Development FA 00.0 Sep. 2019

Program Management Documents

 

Document Number

Document Title

Dated

1

G01 NRDC Consent Order vs SCDHEC

Consent Order of Dismissal Docket No 07-ALJ-07-121-CC (Regarding SCDHEC issuance of Modified Permit for SRS Z-Area Saltstone Disposal Facility.)

Aug. 2007

2

G02 SRNS-RP-2019-00657

Federal Facility Agreement Annual Progress Report for Fiscal Year 2019

Nov. 2019

3

G03 SRNL-STI-2009-00512 Rev 0

Savannah River Site DOE 435.1 Composite Analysis

Jun. 2010

4

G04 SRNS-TR-2008-00101 Rev. 3

Savannah River Site Approved Site Treatment Plan, 2011 Annual Update

Nov. 2011

5

G05 SRR-CWDA-2016-00083 Rev 3

SCDHEC Permit Summary

Feb. 2018

6

G06 SRR-RP-2014-00926 Rev 1

SRR, LLC Integrated Safety Management System Description Document

Dec. 2015

7

G07 WSRC-IM-2004-00008 Rev 1

DSA Support Document - Site Characteristics and Program Descriptions

Jun. 2007

8

G08 WSRC-OS-94-42 ADN 89-05-FF

Federal Facility Agreement for the Savannah River Site (includes FY2015 Approved Appendices)

Aug. 1993

9

G09 Manual 1B Proc 1.29 Rev 3

Management Requirements and Procedures - SRS Interface Agreement Development Process

Jan. 2015

10

G10 Manual 6Q Proc EMPP 6Q-001 Rev 10

Manual Number 6Q, Procedure EMPP 6Q-001 Rev 10, Standards for Development and Maintenance of an Emergency Planning Hazards Assessment (EPHA)

Nov. 2010

11

G11 Manual 3Q Proc 4.14 Rev 9

Environmental Compliance Manual 3Q Asbestos Management Program Procedure 4.14

Nov. 2013

12

G12 SRNL-STI-2018-0003 Rev 0

FY 2017 SRS Composite Analysis Annual Review

Apr. 2018


Salt and Sludge Batch Qualification Documents

 

Document Number

Document Title

Dated

1

H01 SRR-LWP-2019-0009 Rev 0

Salt Batch Plan in Support of Liquid Waste System Plan Rev 21

Mar. 2019

2

H02 SRR-LWP-2019-0008 Rev 1

Sludge Batch Plan in Support of Liquid Waste System Plan Rev 21

Jul. 2019

3

H03 X-ESR-S-00136 Rev 1

Evaluation of Sludge Batch 8 Qualification with ISDP Salt Batches 6D Compliance to DWPF Waste Acceptance Criteria

Feb. 2014

4

H04 X-ESR-H-00739

Rev 0 Evaluation of ISDP Batch 8 Qualification Compliance to 512-S, DWPF, Tank Farm, and Saltstone Waste Acceptance Criteria

Feb. 2015

5

H05 SRR-WSE-2013-00104

Rev 0 Saltstone Formulation Guidance for Shift Engineering Support

Nov. 2013

6

H06 X-ESR-S-00294 Rev. 1

Evaluation of Sludge Batch 9 Qualification with ISDP Salt Batches 8 and 9 Compliance to DWPF Waste Acceptance Criteria

Aug. 2016


Saltstone Facility Documents

 

Document Number

Document Title

Dated

1

I01 G-SD-Z-00002 Rev 11

System Design Document for Saltstone Structures and Vaults

Aug. 2017

2

I02 G-SD-Z-00003 Rev 14

System Design Description Saltstone Process

Jun. 2019

3

I03 G-SD-Z-00004 Rev 8

System Description Document for Saltstone Electrical

Jun. 2019

4

I04 G-SD-Z-00005 Rev 5

System Design Description for Saltstone HVAC

Jul. 2013

5

I05 G-SD-Z-00006 Rev 7

System Description Document for Saltstone Support

Jun. 2019

6

I06 G-SD-Z-00007 Rev 5

System Description Document for Saltstone Laboratory

May 2013

7

I07 G-SD-Z-00008 Rev 4

System Description Document for Saltstone Fire Protection

Oct. 2005

8

I08 M-DCP-Z-11003 Rev 1

DCP SILO Bin Aeration System and Slide Gate Valves Modifications

Jun. 2019

9

I09 M-DCP-Z-11002 Rev 1

Pre-Mix Screw-Feeder Replacement

Sep. 2012

10

I10 M-DCP-Z-11004 Rev 1

Fly Ash Silo #2 Vent Dust Collector Upgrade

Aug. 2019

11

I11 N-AA-Z-00001 Rev 6

DOE-SR and SRR Authorization Agreement for the Saltstone Facility

Aug. 2019

12

I12 SRR-CWDA-2014-00006 Rev 2

FY2014 Special Analysis for the Saltstone Disposal Facility at SRS

Sep. 2014

13

I13 SRR-CWDA-2015-00069

Rev 0 Impact Assessment of Mercury Uncertainties within the SDF PA and SDF Special Analysis

May 2015

14

I14 S-TSR-Z-00002 Rev 17

Saltstone Technical Safety Requirements

Jan. 2019

15

I15 SRR-CWDA-2013-00050 Rev 1

Evaluation of SDUs 3A, 3B, 5A, and 5B As-Built Conditions to Support Unreviewed Waste Management Question Evaluation

Jun. 2013

16

I16 SRR-CWDA-2014-00070 Rev 0

Evaluation of Potential Breach of Side Wall High Density Polyethylene (HDPE) Liner on SDU Cell 3A

Mar. 2012

17

I17 WSRC-IM-2004-00028 Rev 87

Pending Changes to the Saltstone Facility Safety Basis Manual

Jun. 2019

18

I18 WSRC-SA-2003-00001 Rev 15

Saltstone Facility Documented Safety Analysis

Jul. 2018

19

I19 X-SD-Z-00001 Rev 18

Waste Acceptance Criteria for Aqueous Waste, Sent to the Z-Area Saltstone Production Facility

Oct. 2018

20

I20 U-ESS-Z-00001 R0

ESS Evaluation of the Safety of the Situation (ESS): Higher than Expected Concentration of Methyl Mercury in Tank 50 (PISA PI-2015-0007)

May 2015

21

I21 SRR-CWDA-2015-00169 Rev 0

Evaluation of Principal SDU Design Features to Inform Future Optimization

Dec. 2015

22

I22 SRR-SDU-2014-00020 Rev 4

SDU6 Lessons Learned Application to SDU7

Jun. 2017

23

I23 Y-AES-Z-00002 Rev 0

Saltstone Disposal Unit (SDU) 6 Floor and Roof Repair Study

Mar. 2016

24

I24 [No Document #]

Petrographic Analysis of Concrete Core Samples from Saltstone Disposal Unit #6 at the SRS, Aiken, SC

Mar. 2016

25

I25 SRR-SDU-2015-00006 Rev 1

SDU6 Tank Cracking SME Reports

Apr. 2016

26

I26 X-ESR-G-00048 Rev 2

Volatilization and Flammability Characteristics of Elemental and Organic Mercury

Jun. 2015

27

I27 M-TC-Z-00008 Rev 6

Task Requirements and Criteria Document Saltstone Facility Disposal Unit #6 Project, Bldg. 451- 006Z

Jun. 2013

28

282 N-NCS-Z-00001 Rev 13

Nuclear Criticality Safety Evaluation for Z-Area

Feb. 2018

29

I29 SRR-CWDA-2016-00064 Rev 0

Assessment of Iodine-129 Disposition in the Northern Portion of the Saltstone Disposal Facility

May 2016

30

I30 N-CLC-Z-00021 Rev 0

Calculation Cover Sheet for Salt Solution Receipt Tank (SSRT) Dose Rate and Shielding Evaluation

Nov. 2012

31

I31 N-ECA-Z-00002 Rev 0

Engineering Calculation Amendment (ECA) Cover Sheet for Salt Solution Receipt Tank (SSRT) Dose Rate and Shielding Evaluation

Dec. 2015

32

Reserved

 


Salt Waste Processing Facility (SWPF) Documents

 

Document Number

Document Title

Dated

1

K01 SWPGGS01HO-0100 Rev 1

SWPF Overview Course Student Handout

 

2

K02 F-FHA-J-00001 Rev 3

Fire Hazards Analysis

Aug. 2019

3

K03 F-SD-J-00001 Rev 3

Fire Detection / Protection

Jul. 2019

4

K04 P-CDM-J-00001 Rev 7

Configuration Management Plan

Apr. 2019

5

K05 P-DB-J-00003 Rev 5

Process Basis of Design

Feb. 2016

6

K06 P-DB-J-00004 Rev 7

Balance of Plant Basis of Design

Mar. 2017

7

K07 P-ESR-J-00011 Rev 3

Operations Requirements Document

Apr. 2015

8

K08 P-FDD-J-00001 Rev 2

Analytical Laboratory Design Requirements

Aug. 2007

9

Reserved

 

10

K10 P-SUP-J-00001 Rev 2

Commissioning Plan

Dec. 2018

11

K11 P-SYD-J-00001 Rev 5

Sequence of Operations

Sep. 2014

12

K12 P-ESR-J-00013 Rev 2

Analytical Laboratory Operation Plan

Jan 2018

13

K13 S-CIP-J-00004 Rev 5

Radiation Protection Program (RPP) for 10 CFR 835 (Occupational Radiation Protection)

Feb. 2017

14

K14 S-EIP-J-00001 Rev 2

Environmental Plan

Nov. 2007

15

K15 N-NCS-J-00001 Rev 1

Nuclear Criticality Safety Evaluation – Fissile Concentration Due to MST

Dec 2016

16

K16 S-RCP-J-00001 Rev 4

Standards/Requirements Identification Document

Sep. 2017

17

K17 S-SAR-J-00001 Rev 1

Documented Safety Analysis

Sep. 2019

18

K18 V-QP-J-00001 Rev 8

SWPF Project Quality Assurance Plan

Jul. 2018

19

K19 P-ESR-J-00035 Rev 7

Cognizant System Engineering Plan

Feb. 2019

20

K20 F-PP-J-00001 Rev 4

Fire Protection Program Plan

Sep. 2019

21

Reserved

 

22

Reserved

 

23

K23 Q-PLN-J-0100 Rev 2

Environmental Management Systems Program Description

Mar. 2019

24

K24 S-CIP-J-00003 Rev 15

10CRF851 Worker Health and Safety Program

Jan. 2020

25

K25 P-EIP-J-00001 Rev 6

Integrated Safety Management System Description

Jan. 2019

26

K26 PL-SH-4300 Rev 7

Industrial Hygiene Program Plan

Nov. 2019

27

K27 J-SD-J-00002 Rev 5

Instrumentation and Controls System Description

Sep. 2019

28

K28 M-SD-J-00004 Rev 2

Heating, Ventilating, and Air Conditioning System Description

Aug. 2019

29

K29 M-SD-J-00005 Rev 1

Utilities System Description

Sep. 2019

30

K30 M-SD-J-00006 Rev 3

Material Handling System Description

Aug. 2019

31

K31 X-SD-J-00001 Rev 2

Alpha Strike Process System Description

Sep. 2019

32

K32 X-SD-J-00002 Rev 3

Caustic-Side Solvent Extraction System Description

Oct. 2019

33

K33 X-SD-J-00003 Rev 2

Cold Chemical Area System Description

Oct. 2019

34

K34 X-SD-J-00004 Rev 2

Alpha Finishing Process System Description

Sep. 2019

35

K35 X-SD-J-00005 Rev 3

Drains System Description

Oct. 2019

36

K36 X-SD-J-00006 Rev 2

Sampling System Description

Sep. 2019

37

K37 X-SD-J-00007 Rev 2

Air Pulse Agitators System Description

Oct. 2019

38

K38 P-RPT-J-00028 Rev 0

Next Generation Solvent Test Report Including a Higher Concentration Waste Demonstration

Mar. 2015


Tank Farm Documents

 

Document Number

Document Title

Dated

1

L01 C-ESR-G-00003 Rev 17

SRS High Level Waste Tank Crack and Leak Information

Feb. 2019

2

L02 S-TSR-G-00001 Rev 59

CSTF Technical Safety Requirements

Dec. 2019

3

L03 WSRC-IM-2003-00010 Rev 68

CSTF Program Description Documents (PDDs)

Dec. 2019

4

L04 N-AA-G-00001 Rev 8

Authorization Agreement (AA) for the Concentration, Storage, and Transfer Facilities (CSTF)

Dec. 2018

5

L05 SRR-CES-2016-00005 Rev 1

Mercury Phase II Study – Mercury Behavior in Salt Processing Flowsheet

Jul. 2016

6

L06 SRR-CWDA-2010-00128 Rev 1 w Apps

Performance Assessment for the H-Tank Farm at SRS

Nov. 2012

7

L07 SRR-CWDA-2011-00022 Rev 0

Industrial Wastewater General Closure Plan for H-Area Waste Tank Systems (IWC Permit #17,424- IW)

May 2012

8

L08 SRR-CWDA-2013-00091 Rev 1

Industrial Wastewater Closure Module for Liquid Waste Tank 16H H-Area Tank Farm, SRS (IWC Permit #17,424-IW)

Apr. 2015

9

L09 SRR-CWDA-2014-00003 Rev 0

SRR Waste Removal and Operational Closure Strategy

Jun. 2014

10

L10 SRR-CWDA-2014-00086 Rev 0

Industrial Wastewater Closure Module for Liquid Waste Tank 12H H-Area Tank Farm, SRS

May 2015

11

L11 SRR-CWDA-2014-00106 Rev 1

Tank 16 Special Analysis for the Performance Assessment for the H-Tank Farm at the SRS

Feb. 2015

12

L12 SRR-CWDA-2015-00019 Rev 1

Removal of Highly Radioactive Radionuclides for Tank 16

Apr. 2015

13

L13 SRR-LWP-2010-00001 Rev 64

SRS Waste Tank Levels (chart)

Sep. 2019

14

L14 U-ESS-G-00002 Rev 2

Evaluation of the Safety of the Situation (ESS): Vulnerabilities Associated with Gas Release Mode Evaluations and Application of Trapped Gas Release Information for Sludge (PISA PI-2014-0007)

May 2016

15

L15 U-ESS-G-00003 Rev 0

Evaluation of the Safety of the Situation (ESS): Management of Mercury Hazards in Tank Farm Evaporators (PISA PI-2015-0001)

Feb. 2015

16

L16 U-ESS-G-00005 Rev 0

Evaluation of the Safety of the Situation (ESS): Vulnerabilities Associated with Waste Tank Overflow (PISA PI-2015-0008)

Jun. 2015

17

L17 WSRC-IM-94-10 Rev 660

LWD/WS Projects Safety Basis Manual

Jan. 2016

18

L18 WSRC-SA-2002-00007 Rev 20

Concentration, Storage, and Transfer Facilities - Documented Safety Analysis - Volume I

Aug. 2017

19

L19 WSRC-SA-2002-00007 Rev 20

Concentration, Storage, and Transfer Facilities - Documented Safety Analysis - Volume 2

Aug. 2017

20

L20 WSRC-SA-2002-00007 Rev 20

Concentration, Storage, and Transfer Facilities - Documented Safety Analysis - Volume 3

Aug. 2017

21

L21 WSRC-SA-2002-00007 Rev 20

Concentration, Storage, and Transfer Facilities - Documented Safety Analysis - Volume 4

Aug. 2017

22

L22 WSRC-TR-2003-00048 Rev 5

Waste Characterization System Program Description Document

Jun. 2017

23

L23 X-SD-G-00005 Rev 35

Waste Compliance Plan - Transfers from DWPF to H tank Farm

Mar. 2018

24

L24 X-WCP-H-00014 Rev 25

Tank 50 Waste Compliance Plan for Transfer to Saltstone

Mar. 2019

25

L25 SRR-LWE-2011-00100 Rev 0

Tank 4 Bulk Waste Removal Complete Determination

Mar. 2011

26

L26 Y-AES-G-00013 Rev 0

Liquid Waste System Mercury Removal Study

Nov. 2015

27

L27 X-SD-G-00009 Rev 2

Waste Acceptance Criteria for Liquid Waste Transfers to the Tank Farms

Oct. 2019

28

L28 ORNL-TM-2013-224 Rev

Next Generation Solvent Development for Caustic-Side Solvent Extraction of Cesium

Jun. 2013

29

L29 X-ESR-S-00057 Rev 0

Evaluation of Interim Salt Disposition Project (ISDP) Macrobatch Dilution Bases Experienced at Actinide Removal Process and Modular Caustic Side Solvent Extraction Unit (ARP/MCU)

Apr. 2012

30

L30 X-CLC-H-00958 Rev 4

MCU Next Generation Solvent Implementation

Aug. 2015

31

L31 SRR-CES-2015-00012 Rev 1

Evaluation of Mercury in Liquid Waste Processing Facilities Phase I Report

Aug. 2015

32

L32 N-ESR-G-00001 Rev 902

High Level Waste Emergency Response Data and Waste Tank Data

Jan. 2020

33

L33 X-ESR-H-00463 Rev 0

Tank 15H Flowsheet

Feb. 2013

34

L34 WSRC-TR-2002-00327 Rev 9

CSTF Corrosion Control Program

Dec. 2015

35

L35 WSRC-TR-2002-00403 Rev 28

Tank Farm Transfer Control Program, Pump Tank Transfer Jet Control Program, and Waste Tank Chemical Cleaning Program

Jul. 2019

36

L36 WSRC-TR-2003-00087 Rev 34

CSTF Flammability Control Program

Nov. 2019

37

L37 X-WCP-H-00008 Rev 19

Waste Compliance Program for Liquid Waste Transfers from H-Canyon to 241-H Tank Farm

Oct. 2019

38

L38 SRR-ESH-2015-00090 Rev 0 Tank Vapor Action Plan

Savannah River Remediation Tank Vapor Action Plan

Sept. 2015


H Tank Farm Tank 48 Documents

 

Document Number

Document Title

Dated

1

M01 Y-RAR-H-00057 Rev 2

Tank 48 Disposition Project Risk Analysis Report

Mar. 2006

2

M02 SRR-CES-2012-00018 Rev 0

Tank 48 Chemical Destruction-Flow Sheet Options Report

May 2012

3

M03 G-ADS-H-00011 Rev 0

Tank 48H Return to Service Systems Engineering Evaluation (SEE) Results Report

Apr. 2006

4

M04 G-TC-H-00051 Rev 1

Tank 48 Disposition by Small Tank Catalyzed Peroxide Oxidation of Tank 48 Tetraphenylborate

Aug. 2012

5

M05 G-ADS-H-00007 Rev 0

Tank 48 Disposition Project WSRC In-House Treatment Option Evaluation

Jun. 2005

6

M06 SRR-CES-2011-00069 Rev 0

Results of Tank 48 Alternatives Table-Top Engineering Evaluation

Oct. 2011

7

M07 SRNL-STI-2012-00342 Rev 1

Results of Copper Catalyzed Peroxide Oxidation (CCPO) of Tank 48H Simulants

Dec. 2012

8 M08 Y-RAR-H-00065 Rev 5 Tank 48 Treatment Process Risk & Opportunity Analysis
Oct. 2010
9 M09 SRR-CES-2011-00066 Rev 1 Technology Maturation Plan Small Tank Catalyzed Peroxide Oxidation of Tank 48 Tetraphenylborate Aug. 2012

Tank Closure Cesium Removal (TCCR) Documents

 

Document Number

Document Title

Dated

1

N01 SRR-CWDA-2015-00112 Rev 3 Eval of TCCR DSS

Evaluation of the Decontaminated Salt Solution Resulting from the Proposed Savannah River Site Tank Closure Cesium Removal Operations

Jun. 2016

2

N02 RFP No. CRP-TC

Request for Proposal (RFP) Tank Closure Cesium Removal (TCCR)

Aug. 2015

3

N03 DSB SBV CRP/TC Rev 0

Draft of TCCR System Specification Subcontract

Aug. 2015

4 N04 U-SBS-H-00026 Rev 0 TCCR Project Safety Basis Strategy Sep. 2019
5 N05 X-SOW-H-00002 Rev 4 Statement of Work - Tank Closure Cesium Removal (TCCR) System Mar. 2017